Home EV Charger Guide: Wallbox Installation, 11 vs 22 kW and Costs
For most electric car owners, an 11 kW wallbox installed by a qualified electrician is the right home charger: it refills a typical battery overnight, needs only a notification to the grid operator in Germany, and costs from a few hundred euros for the unit. A 22 kW wallbox charges twice as fast only if your car's on-board charger accepts 22 kW of AC power, and in Germany it needs the grid operator's approval. Charging from an ordinary household socket works in an emergency but is not recommended for regular use.

Key takeaways
- An 11 kW wallbox needs a three-phase supply at 16 A per phase; a 22 kW wallbox needs 32 A per phase (ADAC).
- The car's on-board charger sets the limit: with a 16 A charger, 11 kW is all the car can take.
- ADAC's installation service listed about €500 for a simple job and about €1,250 to €2,200 with a new cable run in 2026; over 70 % of single-family installations cost less than €1,500.
- In Germany every wallbox must be reported to the grid operator, and units above 11 kW need approval, which can take up to two months.
Socket, 11 kW or 22 kW: the options compared
| Option | Supply | Power | Notes |
|---|---|---|---|
| Household socket with portable charger | Single-phase, up to 16 A | Up to about 3.7 kW | ADAC does not recommend it for regular charging |
| Single-phase wallbox | Single-phase, 32 A | Up to 7.4 kW | Where only a single-phase supply is available |
| 11 kW wallbox | Three-phase, 16 A per phase | 11 kW | ADAC's recommendation for most households |
| 22 kW wallbox | Three-phase, 32 A per phase | 22 kW | Only useful if the car accepts 22 kW AC |
The figures assume the usual European 230 V per phase. Wikipedia gives 3.68 kW for a Schuko socket at 230 V and 16 A, and 7.4 kW for single-phase charging at 32 A.
Why the car decides the charging speed
The wallbox does not charge the battery directly. On AC charging, it supplies power to the car's on-board charger, which converts it to DC for the battery. That charger has its own limit. ADAC's rule is simple: if the on-board charger supports up to 16 A on one, two or three phases, an 11 kW wallbox is fully sufficient. Only a 32 A on-board charger makes a 22 kW wallbox worth considering.
A car with a single-phase on-board charger cannot use all three phases of an 11 kW wallbox. Check the AC charging power in the car's specifications before choosing. You can find the battery size and other data for each model on our electric cars pages.

How long home charging takes
Charging time is roughly the energy you need divided by the charging power, which is the formula ADAC uses. The table applies it; real sessions take longer because of charging losses. ADAC gives 5 to 8 hours as typical for a full charge at 11 kW.
| Energy to add | 3.7 kW socket | 7.4 kW single-phase | 11 kW three-phase | 22 kW three-phase |
|---|---|---|---|---|
| 20 kWh | 5 h 25 min | 2 h 40 min | 1 h 50 min | 55 min |
| 40 kWh | 10 h 50 min | 5 h 25 min | 3 h 40 min | 1 h 50 min |
| 60 kWh | 16 h 15 min | 8 h 5 min | 5 h 25 min | 2 h 45 min |
| 80 kWh | 21 h 40 min | 10 h 50 min | 7 h 15 min | 3 h 40 min |
The pattern is clear. With 11 kW, almost any car is full by morning. A 22 kW wallbox saves time mainly for people with very high daily mileage or several cars sharing one charger. ADAC points out that 11 kW is gentler on the battery, while 22 kW has slightly lower charging losses because sessions are shorter.
What a wallbox costs
ADAC's figures for the unit:
| Wallbox | Price range listed by ADAC |
|---|---|
| Simple models | About €200 to €500 |
| Mid-range models | About €500 to €1,000 |
| Premium models | From about €1,000 |
| ADAC shop offers (2026) | 11 kW from €410, 22 kW from €554, including VAT |
ADAC says the price depends mainly on the manufacturer and the features, not on the charging power.
Installation is often the larger part. ADAC's installation service for single-family houses listed three typical packages in 2026:
| Installation job (ADAC service, 2026) | Price |
|---|---|
| Mounting at a prepared connection, commissioning, configuration and grid registration | About €500 |
| Cable run up to 10 m, up to two wall penetrations, residual-current device and circuit breaker | About €1,250 |
| Cable run up to 20 m, up to three wall penetrations, protection devices and surge protection | About €2,200 |
Digging work and a new meter cabinet are extra. ADAC also notes that if the property's total power demand exceeds 30 kW, the grid operator charges a connection contribution, about €500 on average (ADAC, 2025). To see how a wallbox changes the cost of running an electric car, add it to the purchase costs in our cost of ownership calculator.
Installation step by step
- Check your supply. Find out whether the house has a three-phase connection and enough spare capacity. ADAC offers a video check for €89 or an on-site check for €199 (2026); any electrician can do the same assessment.
- Choose the wallbox to match the car. For most cars, an 11 kW unit. Decide on a fixed (tethered) cable or a socket for your own cable.
- Get a quote from a qualified electrician. In Germany only a qualified electrician may install and commission a wallbox; self-installation is not allowed.
- Notify the grid operator. The electrician usually does this, but confirm it is in the quote. The grid operator is not the same company as your electricity supplier.
- Install the protection devices. ADAC lists protection against DC fault currents above 6 mA and AC fault currents above 30 mA as mandatory. Many wallboxes have the DC protection built in.
- Commission and test. The installer sets the maximum current, the app and any load management.
Rules in Germany: notification, approval and grid control
Rules on home chargers are set nationally, so check with your local grid operator or electrician if you live elsewhere. Germany is a well-documented example:
- Every wallbox must be notified to the grid operator before installation, whatever its power. This has applied since March 2019 under the Low Voltage Connection Ordinance (NAV), and also covers mobile chargers on adapters. Notification is free.
- Above 11 kW, approval is needed. The grid operator must respond within two months; after approval you have four months to install. A 22 kW wallbox limited to 11 kW usually needs no approval.
- Controllable charging since 2024. New wallboxes above 4.2 kW installed since 1 January 2024 must be controllable by the grid operator, which may reduce them to 4.2 kW for short periods in an emergency. In return, the grid operator may not refuse or delay the connection because of possible grid overload.
- Unreported wallboxes can lead to claims for damages and to the power being cut off, ADAC warns.
Tenants need the landlord's consent before installing a wallbox. In flats owned by several parties, ADAC says the owners' association can no longer block a charging point for an owner's parking space under the WEMoG law, although the other owners still have a say in how it is installed.
Charging from a normal socket
A portable charger plugged into a household socket is useful when travelling or as a backup. For daily charging, ADAC says it is not to be recommended. Even at the socket's maximum of about 3.7 kW, adding 40 kWh takes almost 11 hours, and many evenings are shorter than that.
Note that in Germany the notification duty also covers mobile chargers used with adapters. If you plan to rely on a socket for a while, have an electrician check the circuit first and use the charger supplied or approved by the car maker.
Try our calculator
Cost of ownership calculatorFAQ
Do I need an 11 kW or a 22 kW wallbox?
For most homes and most cars, 11 kW. It fills a typical battery overnight and needs only a notification in Germany. A 22 kW unit helps only if the car's on-board charger accepts 22 kW AC and the house supply can take it.
How much does it cost to install a home charger?
ADAC's installation service listed about €500 for mounting at a prepared connection and about €1,250 to €2,200 with a new cable run and protection devices in 2026. ADAC listed wallboxes themselves from about €200 to over €1,000 in 2026.
Can I install a wallbox myself?
Not in Germany: only a qualified electrician may install and commission it, regardless of your own skills. Elsewhere, check national rules before any work on the fixed installation.
Can I charge an electric car from a normal socket?
Yes, with the portable charger supplied by the car maker, but ADAC does not recommend it for regular use. At up to about 3.7 kW it is slow: a 40 kWh top-up takes almost 11 hours.
Do I need permission for a wallbox?
In Germany every wallbox must be reported to the grid operator, and units above 11 kW need its approval. Tenants also need the landlord's consent. Elsewhere, ask your grid operator or electrician about local rules.
Sources
- ADAC: Wallbox 11 oder 22 kW (accessed 23 Oct 2026)
- ADAC: Wallbox-Installation (accessed 23 Oct 2026)
- ADAC: Wallbox fürs Elektroauto anmelden (28.11.2025) (accessed 23 Oct 2026)
- Wikipedia: Charging station (accessed 23 Oct 2026)